Property developers who request the installation of an electric distribution system to serve a subdivision or commercial property should contact Carroll Electric Cooperative as early as possible in their project planning process to obtain and provide the Cooperative's development standards to any engineers or contractors. 


Residential Developments

Ryan Butler
1-800-432-9720, Ext. 1415 

Commercial Developments
Brian Wise
1-800-432-9720, Ext. 2694

 


What are Carroll Electric's Standards for Residential Development?

To view Carroll Electric's Standards for Residential Developments, click here.

When should I make application and pay my design deposit?

We recommend making an application as early as possible.  A good rule of thumb would be to apply at the same time you submit plans to the local planning jurisdiction.

How long does it take for Carroll Electric to design my project once I submit an application?

Typically Carroll Electric will need 45-60 days to prepare a design and cost estimate for a new project.

When will Carroll Electric acquire materials for my project and how long does that take?

Materials will be ordered once the developer has signed an agreement, made the required payments, and submitted their performance bond.  Material acquisition typically takes 12-16 weeks (on average).

 


 To request more information about Carroll Electric's Development Standards, please submit the following information:

(jpg, jpeg, png, pdf, dwg)





If you are NOT a developer but are building a single, residential home, refer to our application for service 
webpage