PLANNING FOR SERVICE

Developers who request the installation of an electric distribution system to serve a subdivision should contact Carroll Electric Cooperative as early as possible in their project planning process to obtain and provide the Cooperative’s development standards to an engineers or contractors.

Residential Developments Contact

Justin Burgess
1-800-432-9720, Ext. 1464

 

To begin the Residential Development process, please complete an application:

 

 

A residential development application may be submitted electronically, by email, or by mail.

Please return all required documents to Carroll Electric Cooperative:

by email to: developments@carrollecc.com

by mail to:   Carroll Electric Cooperative 

Attn: Justin Burgess

PO Box 4000

Berryville, AR 72616

 


What are Carroll Electric's Standards for Residential Development?

To view Carroll Electric's Standards to Residential Developments, click here.

When should I make application and pay my design deposit?

We recommend making application as early as possible. A good rule of thumb would be to apply at the same time you submit plans to the local planning jurisdiction.

How long does it take Carroll Electric to design my project once I submit an application?

Typically, Carroll Electric will need 45-60 days to prepare a design and cost estimate for a new project.

When will Carroll Electric acquire materials for my project and how long does that usually take?

Materials will be ordered once the developer has signed an agreement, made the required payments, and submitted their performance bond. Material acquisition typically takes 12-16 weeks (on average).





If you are NOT a developer but are building a single, residential home, refer to our application for service 
webpage